1 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
IN THE HON’BLE COURT OF THE SPECIAL JUDGE FOR TRIAL AND DISPOSAL OF COMMERCIAL DISPUTES: VISAKHAPATNAM
Present: G. Vallabha Naidu
Special Judge for Trial and Disposal of
Commercial Disputes, Visakhapatnam.
Monday, this the 13th day of June, 2022
COS. No.2 /2018 (Old O.S.No.389/2012) Between: Meka Atchuta Ramarao, aged 46 years, Businessman, son of Late Satyanarayana Murthy, resident of Flat No.204, Sampath Arcade, Narasimha Nagar, Visakhapatnam 530024. …. Plaintiff And:
1. Kakarlapudi Suryanarayana Raju, aged around 68 years, Hindu, S/o. Late Sambasiva Raju, resident of Door No.54-11-66, Gazetted Officers Colony, H.B.Colony, Visakhapatnam 530022.
2. Smt.Kakarlapudi Sarojini Devi, aged around 59 years, Hindu, W/o. Suryanarayana Raju, resident of Door No.54-11-66, Gazetted Officers Colony, H.B.Colony, Visakhapatnam 530022.
3.Vytla Narayana Rao, aged around 48 years, Hindu, S/o. Janaki Ramayya, resident of Door No.50-96-8/2, Seethammadhara (North Extension), Visakhapatnam 530013.
…..Defendants
This suit has come up for arguments before me on 14-03-2022 in the presence of Sri.K.Ravi, Advocate for Plaintiff Sri.V.V.Ravi Prasad & J.V.Rama Krishna, Advocates for D1 & D2 and Sri.N.S.V.Reddy, Advocate for 3rd defendant and this matter having heard and stood over for consideration till this day, this Court delivered the following:
JUDGMENT
1.Suit for (a) mandatory injunction by directing the defendants to execute and register the open spaces etc., of approved layout No.1 of 2008 by way of
Registered Gift Settlement Deed in favour of Kapuluppada Grampanchayat,
Bheemunipatnam Mandal, Visakhapatnam represented by its Panchayat Secretary and for (b) a mandatory injunction by directing the defendants to execute necessary papers and documents so as to obtain release of plots Nos.16 to 34, 84 to 91 of 2 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) approved layout 1/2008 mortgaged in favour of Visakhapatnam Development
Authority, at the cost and expenses of the plaintiff and (c) to specifically enforce the Agreements dt.2-02-2007 and 27-05-2007 by directing the defendants to execute and register, at the cost and expenses of the plaintiff (or) alternatively, if the court comes to the conclusion that Specific Performance cannot be granted in such an event to award compensation of Rs. 2,72,47,320/- (Rupees Two Crores
Seventy Two Lakhs Forty Seven Thousand Three Hundred and twenty only) under
Section 21 of the Specific Relief Act, 1963 and for such other reliefs and for costs of the suit.
2.The averments of the plaint in brief are that:
The plaintiff is engaged in the business of development of layouts and construction of apartments/group housing. The 1st defendant is husband of the 2nd defendant. The 1st defendant was absolute owner of land admeasuring an extent of Ac.4.44 ¼ cents covered by Survey Nos. 85/5, 6,8,9,10,11,12,13,86/1,2,3 of
Kapuluppada village having purchased the same under registered sale deeds. The 2nd defendant was absolute owner of the land admeasuring an extent of Ac.4.93 ½ cents covered by S.Nos.29/5,30/1,86/1,3,4 of Kapuluppada Village, Kapuluppada
Panchayat, Bheemunipatnam Mandal, Visakhapatnam having purchased the same under registered sale deeds. The total extent of land owned by the defendants 1 & 2 was Ac.9.37 ¾ cents. It is further averred in the plaint that the defendants 1 & 2 jointly entered into a Development Agreement on 22-02-2007 and the said agreement contained mutual rights and reciprocal obligations. As per the terms of the said Development Agreement, the plaintiff agreed to develop the said extent into a layout of house plots at his own cost and expenses and obtain necessary approvals from Visakhapatnam Urban Development Authority (VUDA) and 3 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Greater Visakhapatnam Municipality Corporation (GVMC). As per clauses 6, 8, & 9 of the said agreement, the plaintiff shall be entitled to 26% of the plotted area while defendants 1 & 2 are entitled to the remaining 74% of the plotted area. The defendants 1 & 2 having agreed to register on completion of B.T Roads and drainages 15% out of the total 26% of the developer’s share and the remaining 11% shall be registered, after the completion of the project as per Visakhapatnam
Urban Development Authority (VUDA) norms in favour of the plaintiff or his nominees. It is further averred in the plaint that the 1st defendant was also in possession and enjoyment of land of an extent of Ac.0.49 ¾ cents under three registered sale agreements cum General Power of attorneys which was also offered for development of layout, on the same terms and conditions, though the same is not mentioned in the development agreement between the plaintiff and the defendants 1 &2. The 3rd defendant was absolute owner of land of an extent of
Ac.0.82 ½ cents covered by S.Nos. 85/5 and 30/7 of Kapuluppada Village,
Kapuluppada Panchayat, Bheemunipatnam having purchased the same under registered Sale Deed. The 3rd defendant entered into a Development Agreement in respect of the above said land on 27-05-2007 with the plaintiff. The plaintiff agreed to develop the said extent along with the extent owned and possessed by defendants 1 & 2. All the terms and conditions of the Development Agreement between the plaintiff and 3rd defendant including sharing pattern and stage of registration of plots are similar to the Development Agreement entered by the plaintiff with the Defendants 1 &2. It is further averred in the plaint that during the actual working out of the layout plans, the 1st defendant had contributed for development of layout only an extent of Ac.4.37 ½ cents out of the total extent purchased by him under registered Sale Deeds together with the extent of Ac.0.49 ¾ cents possessed by him under Registered Sale Agreement cum General Power of 4 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Attorneys. Similarly, the 2nd defendant had contributed only an extent of Ac.4.58 ¾ cents. The 3rd defendant had similarly contributed only an extent of Ac.0.72 ½ cents. It is further averred in the plaint that the plaintiff thereafter developed a layout of residential house plots in an extent of AC.10.18 ½ cents at his own cost and expenses by obtaining necessary approvals from Visakhapatnam Urban
Development Authority in the name of the defendants. The said layout was given
L.P.No.1/2008. As per the approval layout plan the total number of plots are 101 and the total plotted area is 28748.62 square yards. The share of the defendants 1 &2 works out to 26,701.79 square yards being the proportionate share for the extent of AC.9.46 cents out of the total extent of AC.10.18 ½ cents. Out of this 26,701.79 square yards, the defendants 1 & 2 are entitled to 19,759.32 square yards while the plaintiff is entitled to the remaining 6942.46 square yards. It is further averred in the plaint that the share of the 3rd defendant works out to 2046.38 square yards being the proportionate share for the extent of AC.0.72 ½ cents out of total extent of AC.10.18 ½ cents. Out of these 2,046.38 square yards the 3rd defendant is entitled to 1514.32 square yards while the plaintiff is entitled to the remaining 532.05 square yards. It is further averred in the plaint that at the request of the defendants 1 & 2, the defendants 1 to 3 being the land owners have sold and registered plot Nos. 77,79 & 80 on 17-09-2008 to the nominees of defendants 1 &2 out of the entitlement of defendant Nos. 1 & 2. Thereafter it was mutually agreed that the respective plots of each sharer should be ear-marked and for that purpose the approved layout consisting of 101 plots should first be grouped into convenient blocks and accordingly 10 blocks were identified. It was agreed that the plaintiff should take Block No.1 i.e., Plot Nos. 76,78,81 & 82 admeasuring 1061 square yards and the remaining extent of plot No.79 admeasuring 112.34 square yards. In
Block No.III, Plot Nos. 92 to 101 admeasuring 2849.28 square yards, in Block 5 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
No.V Plot Nos. 64 to 73 admeasuring 2666.60 square yards. The 3rd defendant agreed to take Plot Nos. 83,85,86,87,90 and 91 admeasuring 1509.30 square yards and the plaintiff should take Plot Nos.84,88 and 89 and defendants 1 & 2 should take the remaining plots. It is further averred in the plaint that even after such ear- marking, the plaintiff will still be short of an extent of 47.47 square yards towards his share which has to be adequately compensated by defendants 1 to 3. Similarly the 3rd defendant will still be short of an extent of 5.04 square yards which has to be adjusted between defendants 1 to 3. It is further averred in the plaint that the defendants had so far registered only plot Nos.93 to 101 of Block No.III admeasuring 2399.96 square yards under seven registered Sale Deeds in the month of November, 2008 and Plot Nos. 81 and 82 of Block No.I admeasuring 533.33 square yards on 13-04-2011 making a total of 2933.29 square yards to the plaintiff’s nominees. Still there is a balance of 4541.22 square yards which is yet to be registered by the defendants i.e., plaint schedule property. It is further averred in the plaint that the plaintiff has completed the development of layout in all respects as per norms of Visakhapatnam Urban Development Authority (VUDA) by spending huge amounts. What remains to be done is only completion of legal formalities i.e., obtaining release of mortgaged plots from Visakhapatnam Urban
Development Authority (VUDA) by paying the requisite amounts, which requires the signatures of the defendants 1 to 3 as owners on the necessary papers, deeds and in the records in the office of Sub-Registrar. Visakhapatnam Urban
Development Authority, however, insists upon transfer of all open spaces, roads and drains to the Kapuluppada Gram Panchayat by a registered settlement deed
before releasing the mortgaged plots. These conditions also become the implied
terms of the contract between the plaintiff and defendants. It is further averred in the plaint that the plaintiff is and has always been ready and willing to perform his 6 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) part of the contract by spending the requisite amount and co-ordinate the same, since it requires the signatures of defendants as owners on the Gift Settlement
Deed and they are not forthcoming to perform their part of the contract. Unless the
Gift Deed is registered in favour of Kapuluppada Gram Panchayat Visakhapatnam
Urban Development Authority will not release the mortgaged plots even though the plaintiff is ready to meet the expenditure. The defendants are not cooperating to execute the documents in spite of several requests made by him. It is further averred in the plaint that the plaintiff has been repeatedly requesting the defendants to register the Gift Settlement Deed in favour of the Kapuluppada Gram Panchayat and obtain release of mortgaged plots and he is ready to meet the requisite expenditure but the defendants have been postponing the same on one pretext or the other. Until and unless both these requirements are met, the layout will not become complete or final because of the procrastination and dilatory tactics of the defendants he was compelled to renew the layout permission up to 5-1-2012 by paying necessary amounts twice. The plaintiff once again applied to VUDA on behalf of defendants 1 to 3, for renewal of layout permission on 19-01-2012 by paying necessary amount and the said application is pending. It is further averred in the plaint that the plaintiff came to know that as per the rules in force VUDA will renew the layout twice for six months each and that thereafter the layout would be cancelled but a further extension/renewal on one time basis, will be given for a period of one year only. So far the VUDA has not cancelled the layout. By way of abundant caution he applied for renewal. If the legal formalities are not completed the layout would become unauthorised. The plaintiff got issued a legal notice dated 18-08-2011 to the defendants stating that if the permission of the layout is not renewed he shall not be held responsible. The defendants who had obtained approval of the layout from VUDA agreeing to abide by and to 7 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) implement the terms and conditions imposed by it while sanctioninglayout are duty bound to comply with them. If the defendants do not register the Gift
Settlement Deed in favour of the Kapuluppada Grampanchayat and do not obtain release of mortgaged plots from VUDA and allow the layout permission to lapse, the layout becomes unauthorised and illegal layout. As per condition No.12 of the layout approval the local authority will not approve or release any building permission until and unless the developmental works are complete and the mortgaged plots are released. It is further averred in the plaint that the plaintiff is seeking mandatory injunction against the defendants to comply with the terms and conditions of the layout approval in addition to seeking specific relief. In response to the notice got issued by the plaintiff, the 3rd defendant gave a reply admitting most of the contents of the notice and expressed his ready and willingness to sign on necessary documents. The defendants 1 & 2 even though received notice they did not give any reply. It is further averred in the plaint that again the plaintiff got issued another legal notice dated 18-05-2012 to all the defendants and they received the same but they did not give any reply. It is further averred in the plaint that the plaintiff spent huge amount for the development of the lay out but he is unable to realise the fruits because of the attitude of the defendants to perform their part of the obligations. The defendants registered seven sale deeds in favour of the nominees of the plaintiff in the month of November, 2008 and eighth sale deed was registered in the month of April, 2011. Had the defendants 1 to 3 promptly registered his remaining extent he would have deployed those funds elsewhere effectively and gained some reasonable profits there from. Under these circumstances, the plaintiff filed the suit praying the Court to pass a decree as prayed for with costs.
8 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
3.The defendants 1 to 3 contested the suit by filing separate written statements denying all the averments made in the plaint. The defendants 1 & 2 filed separate written statements and the 3rd defendant filed separate written statement. The contention of the defendants 1 & 2 as per the written statement filed by them in brief are that:
The suit filed by the plaintiff is not maintainable either under law or on facts as the plaintiff approached this Court basing on an in-admissible document. The development agreement said to have been executed by the defendants is not admissible under law. It is further averred in the written statement of the defendants 1 & 2 that they have contributed another land of an extent of AC.9.46 cents for development purpose by them under Sale Agreement cum-General Power of Attorney. The total area plotted as per layout plan is 28,045.57 square yards.
The total area of land surrendered by them was AC.9.37 ¾ cents plus AC.0.49 ¾ cents totalling AC.9.875 cents whereas the plaintiff showing only AC.9.46 cents. It is further averred in the written statement of the defendants 1 & 2 that there is no ear-marking till today for allocation of plots either owners or developer. As per the
Development Agreement the owners will allot plots to the developer at their choice. It is further averred in the written statement of the defendants 1 & 2 that they registered 14 plots in favour of the nominees of the plaintiff and the total consideration was taken by the plaintiff only. They have contributed AC.9.87 ½ cents and hence the plaintiff is not entitled for any compensation and the plaintiff has to render account for the entire land surrendered by them for development. It is further averred in the written statement of the defendants 1 & 2 that unless the land conversion fee paid the mortgaged plots will not be released. The plaintiff did not pay the conversion charges. The layout was approved in LP No.1/2008 and according to condition No.9 of the above approval, the developmental works shall 9 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) be completed within one year and submit the requisition letter for releasing mortgaged plots. Due to inordinate delay in developing on the part of the plaintiff, the plaintiff has to apply for renewal of the permission by paying requisite amounts, and it is only on account of the plaintiff, but not on account of the defendants. The delay in developing the layout or for payment of the amounts for renewal of the permissions, the plaintiff is solely responsible and the defendants have not committed or violated any conditions of the agreement. It is further averred in the written statement of defendants 1 & 2, in fact all the fourteen plots were sold to the nominees of the plaintiff only. The defendants 1 & 2 never sold any plot to anyone till today. They received notice from the Revenue Divisional
Officer demanding to pay an amount of Rs. 44,35,763/- (Rupees Forty Four Lakhs
Thirty Five Thousand Seven Hundred Sixty Three only) which includes penalty also. It clearly shows that the plaintiff has not completed his part of contract in terms of the development agreement and not rendered the account for the land surrendered to him and also the share of the defendants 1 &2. It is further averred in the written statement of defendants 1 & 2 that the suit is not properly valued for the purpose of court fee. They never denied performing their part of the contract and the plaintiff himself has not satisfied the conditions of the approval accorded by the Visakhapatnam Urban Development Authority(VUDA) for development of the lay out and thereby violated his part of the contract. Due to inordinate delay of more than 4 years in developing the layout the defendants have to forgo their customers, since the layout is not fully developed. It is further averred in the written statement of the defendants 1 & 2 that they are ready and willing to execute the documents that are required if the plaintiff proves that he has fulfilled all the conditions of VUDA. The plaintiff filed the suit with a view to harass the defendants by preventing them from executing the sale deeds in respects of their 10 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) share of plots. Hence, the defendants 1 & 2 pray the Court to dismiss the suit with costs.
4.The contention of the 3rd defendant as per his written statement that he has always been ready and willing to perform his part of the obligations, more particularly, execution and registration of Gift Settlement Deed infavour of
Kapuluppada Gram Panchayat and signing necessary papers/deeds along with officials of the Visakhapatnam Urban Development Authority to get the mortgaged plots released as well as register the plaintiff’s ear-marked plots to him or his nominees. For the reasons best known to the defendants 1 & 2 they are not forthcoming to perform their part of the contract. It is further averred in the written statement of the 3rd defendant that without participation of the defendants 1 & 2 he cannot alone do anything. It is further averred in the written statement of the 3rd defendant that he has no objection to pass a decree in favour of the plaintiff without costs.
5.After filing of the written statement of the defendants 1 to 3 the plaintiff filed rejoinder denying all the averments made in the written statement filed by the defendants 1 & 2. The averments of the rejoinder filed by the plaintiff in brief are that the Visakhapatnam Urban Development Authority while approving the layout fixes the maximum extent of land that can be converted as plots after making provision for Roads, open spaces etc.,. As per the approved plan an extent of
AC.6.04 cents out of AC.10.18 ½ cents alone was permitted to be converted as plots earmarking the rest of extent for roads and open spaces. Therefore, the total extent of land cannot exceed 29,233.60 square yards equivalent to AC.6.04 cents.
It is further averred in the rejoinder that he developed only an extent of 28,045.57 square yards what is converted into layout of plots is an agricultural land which is 11 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) neither square nor rectangle in shape. At the time of approval of layout plan as per norms then prevailing, 25% of the plotted area had to mortgage to VUDA.
Accordingly, an extent of AC.1.51 ½ cents, corresponding to 25% of Ac.6.04 cents was mortgaged to VUDA under registered mortgage deed dated 28-12-2007. It is further averred in the rejoinder that the plaintiff has completed the development of layout in all physical aspects as per the norms of VUDA. What remains to be done is only completion of legal formalities though the competent authority i.e.,
Revenue Divisional Officer issued a notice dated 28-05-2009 demanding payment of an amount of Rs. 44,35,763/- (Rupees Forty Four Lakhs Thirty Five Thousand
Seven Hundred Sixty Three only) earlier the very same authority issued notice
dated 24-06-2008 where under a lesser amount of Rs. 22,92,750/- (Rupees Twenty
Two Lakhs Ninety Two Thousand Seven Hundred Fifty only) is demanded. It is further averred in the rejoinder that there is no time frame fixed by the parties and there was no delay in completion of obligations by the defendants. Hence, he prays the Court to decree the suit as prayed for.
6.Based on the pleadings of both parties to the suit the following issues were settled for trial on 15.04.2013.
1. Whether the plaintiff did develop the layout as agreed?
2.Whether there is inordinate delay in developing the layout?
3.Whether the plaintiff performed his part of contract under
Agreement?
4.Whether the plaintiff fulfilled the conditions imposed by VUDA as agreed?
5.Whether the suit is maintainable for the relief of mandatory injunction to execute gift deed, if so, is the plaintiff entitled to the relief of mandatory injunction for execution of Gift Deed by the defendants?
6.Whether the suit is maintainable for the relief of mandatory injunction to direct the defendants to obtain release of mortgaged plots and if so, 12 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) is the plaintiff entitled for the said relief of mandatory injunction?
7.Is this suit as framed is maintainable?
8.Whether the plaintiff is entitled to the relief of specific performance as prayed for?
9.To what relief?
7.On 01.07.2020 the following additional issues were framed.
1.Whether the plaintiff is entitled to the alternative relief of compensation of Rs. 2,72,47,320 (Rupees Two Crores Seventy Two
Lakhs Forty Seven thousand three hundred and twenty only) as prayed for?
2.Whether the suit is valued properly for the purpose of Court Fee?
8.In order to establish the case of the plaintiff, the plaintiff himself was examined as PW1 and got marked Exs. A1 to A52. On behalf of defendants no oral evidence is adduced and no documents are marked. The learned counsel for defendants 1 & 2 filed a memo stating that there is no oral evidence on behalf of the defendants 1 & 2. As seen from the record admittedly, the 3rd defendant is sailing with the plaintiff and did not cross examine PW1. Even the 3rd Defendant did not adduce any oral evidence to substantiate his contention. The respective Senior
Counsel of plaintiff and defendants 1 & 2 submitted detailed written arguments at length along with citations.
6.ISSUES 1 to 4:
1. Whether the plaintiff did develop the layout as agreed?
2.Whether there is inordinate delay in developing the layout?
3.Whether the plaintiff performed his part of contract under
Agreement?
4.Whether the plaintiff fulfilled the conditions imposed by VUDA as agreed?
To avoid the repetition of discussion all these four issues are clubbed together for the sake of convenience. The onus to prove these issues at the first instance lies 13 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) on the plaintiff as the plaintiff filed the suit against the defendants 1 to 3 for a mandatory injunction by directing the defendants to execute and register at the cost and expenses of the plaintiff, the open spaces etc., of approved layout No.1/2008 by way of registered Gift Settlement Deed in favour of Kapuluppda Gram Panchayat,
Bheemunipatnam Mandal, Visakhapatnam represented by its Panchayat Secretary and for a mandatory injunction directing the defendants to execute necessary papers and documents so as to obtain release of plot Nos. 16 to 34, 84 to 91 of approved layout 1/2008 mortgaged in favour of Visakhapatnam Urban Development
Authority at the cost and expenses of the plaintiff and to specifically enforce the
Agreements dated 22-02-2007 and 27-05-2007 by directing the defendants to execute and register at the cost and expenses of the plaintiff, the plaint schedule property in favour of the plaintiff or his nominees or alternatively, if any reason the
Court comes to the conclusion that Specific Performance cannot be granted, then and only in such an event to Award compensation of Rs. 2,72,47,320/- (Rupees Two
Crores Seventy Two Lakhs Forty Seven thousand Three Hundred and Twenty only) under Section 21 of the Specific Relief Act. If the plaintiff is able to establish his case by adducing oral and documentary evidence, then the burden shifts on the defendants to disbelieve the case of the plaintiff.
7.The learned Senior Counsel for plaintiff submits that the plaintiff is engaged in the business of Development of layouts and construction of Apartments and
Group Housing. The learned Senior Counsel for plaintiff submits that the
Defendants 1 & 2 are husband and wife and the 1st Defendant is the absolute owner of the land admeasuring Ac. 4.44 ¼ cents covered by Sy.Nos. 85/5, 6,8 to 13, 86/1 to 3 of Kapuluppada Village, Kapuluppada Panchayat, Bheemunipatnam Mandal,
Visakhapatnam having purchased the same under registered Sale deeds. The learned
Senior Counsel for plaintiff submits that the 2nd defendant was absolute owner of the 14 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) land admeasuring an extent of Ac. 4.93 ½ cents covered by Sy.Nos. 29/5, 30/1, 86/1, 3, 4 of Kapuluppada Village, Kapuluppada Panchayat, Bheemunipatnam Mandal,
Visakhapatnam having purchased the same under registered sale deeds. The learned
Senior Counsel for plaintiff further submits that the total extent of the land owned by defendants 1 & 2 was Ac.9.37 ¾ cents and the defendants 1 & 2 jointly entered into Development Agreement on 22-02-2007 with the plaintiff. The learned Senior
Counsel for plaintiff further submits that as per the said Development Agreement, the plaintiff has to develop the said extent into a layout of house plots at his own cost and expenses and to obtain necessary approvals from Visakhapatnam Urban
Development Authority and Greater Visakhapatnam Municipal Corporation. The learned Senior Counsel for plaintiff further argued that as per the terms and conditions of the Development Agreement, the plaintiff is entitled 26% of the plotted area and the defendants 1 & 2 are entitled to the remaining 74% of the plotted area and the defendants 1 & 2 have agreed to register on completion of B.T-
Roads and drainages 15% out of the total 26% of the developer’s share and the remaining 11% shall be completed after completion of the project as per the norms of Visakhapatnam Urban Development Authority in favour of the plaintiff or his nominees. The learned Senior Counsel for plaintiff further submits that the 1st
Defendant was also in possession and enjoyment of an extent of Ac.0.49 ¾ cents of land and the same was given for development to the plaintiff. The learned Senior
Counsel for plaintiff further argued that the 3rd defendant was absolute owner of land to an extent of Ac.0.82 ½ cents covered by Sy.No.85/5 and 30/7 of
Kapuluppada Village having purchased the same under registered Sale Deed and the 3rd defendant entered into Development Agreement on 27-05-2007 with the plaintiff and the plaintiff agreed to develop the said extent along with the extent owned and possessed by defendants 1 & 2 and all the terms and conditions of the Development 15 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Agreement between the plaintiff and D3 including sharing pattern is one and the same.
8.In view of the submission made by the learned Senior Counsel for plaintiff, as seen from the record, admittedly, there is no dispute that the defendants 1 to 3 have entered into Development Agreements with the plaintiff to develop the said extents into a layout of house plots at the own cost and expenses of the plaintiff and to obtain necessary approvals from Visakhapatnam Urban Development Authority and
Greater Visakhapatnam Municipal Corporation. As seen from the contents of the written statement filed by the defendants 1 & 2 they are not disputing about the execution of Development Agreement in favour of the plaintiff. Ex.A1 relied upon by the plaintiff is the original Development Agreement dated 22-02-2007 executed in between the plaintiff and the defendants 1 & 2. Ex.A2 relied upon by the plaintiff is the original Development Agreement dated 27-05-2007 executed in between the plaintiff and the 3rd defendant. As seen from the clauses 6, 8 & 9 of Ex.A1 original
Development Agreement dated 22-02-2007 and the original Development
Agreement dated 27-05-2007 under Ex.A2, the plaintiff shall be entitled to 26% of the plotted area and the defendants 1 to 3 are entitled to the remaining 74% of plotted area.
9.The learned Senior Counsel for plaintiff submits that the plaintiff and the defendants 1 to 3 have mutually agreed and ear-marked the respective plots fallen to each share after execution of registered Sale Deeds executed by the defendants 1 & 2 in favour of 3rd parties under the originals of Ex.A6 to A8. The learned Senior
Counsel for plaintiff submits that the sale of plots covered by the originals of
Exs.A6 to A8 Sale Deeds are out of entitlement of defendants 1 & 2 and the plots covered by other Sale Deeds i.e. Exs. A9 to A15 i.e., certified copies of registered
Sale deeds are out of the entitlement of the plaintiff.
16 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
On the other hand, the learned Senior Counsel for defendants 1 & 2 submits that the plots have not been ear-marked and as per the Development Agreement under Ex.A1, the owners will allot plots to the Developer at their discretion. The learned Senior Counsel for defendants 1 & 2 further argued that as per the relevant terms of Ex.A1 Development Agreement, on completion of the Development the
Developer and the owners will ear-mark the plot numbers for their ownership. The learned Senior Counsel for defendants further argued that the plaintiff did not file any iota of document in support of his plea that the plots were earmarked among plaintiff and the defendants. The learned Senior Counsel for defendants 1 & 2 further argued that except the oral say of DW1 there is no documentary proof that the plots are earmarked among the plaintiff and the defendants.
10.In view of the submissions made by the respective Senior Counsel of both parties the burden of proving that the plots were earmarked among the plaintiff and the defendants squarely lies on the plaintiff. If the plaintiff is able to establish the same by adducing oral and documentary evidence then the burden shifts on the defendants that the plots have not been earmarked. The onus to prove that the plots in the layout have been earmarked among the parties to the Development
Agreement under Exs. A1 & A2 and the plots mentioned in paragraphs-III (l) & (m) of the plaint fell to the share of plaintiff and that the plots mentioned in para-III(m) of the plaint fell to the share of 1st defendant and all the remaining plots felt to the share of defends 2 & 3 lies on plaintiff.
11.In view of the submissions made by the respective Senior Counsel of both parties, the point that arises for consideration is: Whether the plots in the layout have been earmarked by the plaintiff and the defendants 1 to 3 for distribution among them towards their respective shares or not and if so whether the particular plots mentioned by the plaintiff in the plaint is falling to his share, to the share of 17 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) defendants 1 to 3 is true and Correct. In order to establish the case of the plaintiff, the plaintiff himself was examined as PW1. As seen from the evidence affidavit of
PW1, he categorically stated at page No.4 of his chief affidavit that he should take in Block-I i.e., plot Nos. 76,78,81,82 admeasuring 1061 square yards and the remaining extent of plot No.79 (odd bit) admeasuring 2849.28 square yards, in
Block No.5 plot Nos. 64 to 73 admeasuring 2666.60 square yards. At page No.5 of his chief affidavit, PW1 further stated that, the 3rd defendant should take in Block
No.II i.e., plot Nos. 83,85,86,87,90 & 91 admeasuring 1509.30 square yards while he should take plot Nos. 84,88 & 89 admeasuring 737.82 square yards. PW1 further stated in his evidence affidavit that the defendants 1 & 2 should take the remaining plots. According to the case of the plaintiff and as per his evidence that after execution of the originals of Exs. A6 to A8 Sale Deeds himself and the defendants 1 to 3 have mutually agreed and earmarked the respective plots falling to each share. On the other hand, the defendants 1 & 2 are disputing about the earmarking of those plots. In order to substantiate the case of the plaintiff, the plaintiff mainly relied upon Exs. A6 to A16 certified copies of registered Sale Deeds said to have been executed by the General Power of Attorney Holder of the defendants 1 to 3 in favour of 3rd parties on various dates. The learned Senior Counsel for plaintiff submits that if there was no earmarking of plots the very purpose of incorporating clause-6 under Exs. A1 & A2 would be frustrated. In view of the submission made by the learned Senior Counsel for plaintiff as seen from the contents of Exs. A1 &
A2 registered Development Agreements clause-6 reads as follows:
“The owners shall register the plots allotted to the Developer share of 15% (out of the total 26%) in favour of the Developer or his nominees/3rd parties after the completion of B.T roads and drainages and the remaining 11% of share shall be registered after the completion of the entire project as per the Visakhapatnam Urban Development norms”.
18 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
12.The learned Senior Counsel for defendants 1 & 2 mainly attacked the plea of the plaintiff basing on the relevant terms i.e., clause No.9 of Ex.A1 Registered
Development Agreement dated 22-02-2007. As seen from the clause No.9 of Ex.A1 it is evident that on completion of development, the Developer and the Owners will earmark plot numbers for their ownership and the Developer shall be entitled for 26% of plots in the land and the owners shall execute and register the regular Sale
Deeds or other conveyance deeds infavour of the Developer/Nominees of the
Developer and the Developer shall have the right to enter into agreements, receive consideration, issue receipts there for, without having to account for the same, execute such deeds in favour of such 3rd parties. Admittedly, except the oral say of
PW1 who is the plaintiff in the suit there is no documentary proof in support of his plea that the plots were earmarked among him and the defendants 1 to 3. As seen from the averments of the plaint and the evidence affidavit of PW1 even though he took a specific plea that plots were ear-marked among them subsequent to sale of plots bearing Nos. 77,79 & 80 on 17-09-2008 he did not mention the time of earmarking. As seen from the cross-examination of PW1 who is plaintiff in the suit, he categorically stated that plots were earmarked among him and the defendants 1 to 3 in the month of October or November, 2008.
13.The learned Senior Counsel for defendants 1 & 2 submits that the timing of alleged fact of earmarking of plots cannot be believed for more than one reason. In order to substantiate his contention he mainly relied upon the recitals mentioned in
Ex.A1 Registered Development Agreement. As seen from the contents of Ex.A1
Registered Development Agreement dated 22-02-2007, it is clear that both parties have agreed for earmarking of plots after completion of the layout. Ex.A3 relied upon by the plaintiff is blue print original approved layout plan. Ex.A4 is true copy of the proceedings dated 05-01-2008 of Visakhapatnam Urban Development 19 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Authority giving permission for approval of layout. As seen from the contents of
Ex.A4 shows that Ex.A3 layout plan was approved in the month of January, 2008 i.e., on 05-01-2008. As seen from the cross-examination of PW1 dated 29-07-2019, he categorically admitted in March or April, 2011 he completed the layout. When the parties to Ex.A1 Development Agreement dated 22-02-2007 and
Ex.A2 Development Agreement dated 25-07-2007 decided to earmark their respective plots after completion of layout, there is no reason why plots were earmarked in the year 2008 itself as per the evidence of PW1 i.e., three years
before completion of layout that too when the layout was in a nascent stage. As
seen from the cross-examination of PW1 at page No.9 of his cross-examination, he categorically admitted that there is no document in proof of allocation and earmarking of plots. PW1 further admitted in his cross-examination at page No.9 allocation and earmarking of plots is very important and vital clause as per their understanding under Ex.A1. PW1 further admitted in his cross-examination that in
October or November, 2008 allocation and earmarking of plots were completed.
He further admitted in his cross-examination that as per Ex.A1 earmarking shall take place on completion of development. PW1 further admitted in his cross- examination that he did not file any paper containing the plots fell to his share.
When the defendants 1 & 2 specifically denying about the earmarking of plotsas alleged by the plaintiff it is for the plaintiff to establish the same by adducing legal and documentary evidence. In the present suit admittedly, the plaintiff has not taken any steps to examine the 3rd defendant who is sailing with him. As seen from the cross-examination of PW1 he categorically admitted that there is no mention in the written statement of D3 about allocation and earmarking of his plots.
14.The other doubtful circumstance to disbelieve the case of the plaintiff about the earmarking of plots is concerned as seen from the recitals of Ex.A1 20 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Development Agreement dated 22-02-2007, it is evident that both parties agreed that 15% of the plotted area out of the share of 26% of plotted area given to the plaintiff’s share shall be registered by the owners infavour of the plaintiff after completion of B.T roads and drainages and remaining 11% share of the plaintiff shall be registered by the owners of the land after completion of the layout as per
Visakhapatnam Urban Development Authority (VUDA) norms. There is absolutely no clause in the Ex.A1 Development Agreement that the owners are entitled to sell some plots of their choice even before completion of B.T roads and drainages, even before completion of layout and even before parties earmarking their respective plots in the layout. Except the sole testimony of PW1 there is no documentary proof to substantiate the plea of the plaintiff that earmarking of plots was over long back among parties to Ex.A1 Development Agreement. Hence, this
Court not inclined to accept the contention of the learned Senior Counsel for plaintiff.
15.The learned senior counsel for plaintiff submits that an adverse inference has to be drawn against the defendants 1 & 2 as the defendants 1 & 2 did not come to the witness box to say anything on oath. On the other hand, the learned Senior
Counsel for defendants 1 & 2 submits that it is for the plaintiff to establish his case and he cannot depend on the weakness of the defendants case. The learned counsel for defendants 1 & 2 further submits that in a suit filed by the plaintiff for specific performance by way of mandatory nature it is for him to establish his case irrespective of the fact whether the defendants 1 & 2 adduced their evidence or not.
16.In view of the submissions made by the respective Senior Counsel of both parties, as seen from the record, admittedly no oral evidence is adduced by the defendants 1 & 2. In a suit filed by the plaintiff for Specific performance of 21 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) contract by way of mandatory injunction directing the defendants to execute and register Gift Settlement Deed in favour of Kapuluppada Panchayat,
Bheemunipatnam, it is for him to establish his case and he cannot depend on the weakness of the defendants case. Admittedly, the defendants 1 & 2 did not come to the witness box to say anything on oath. In order to substantiate the case of the plaintiff, the learned Senior Counsel for plaintiff relied upon a decision of the
Hon’ble Supreme Court reported in AIR 1999 SC pg. 1341, in case between
ISWAR BHAI C. PATEL Vs. HARIHAR BEHERA AND OTHERS, wherein their Lordships of the Hon’ble Supreme Court held that:
“Having not entered into the witness box and having not presented himself for cross-examination, an adverse presumption has to be drawn against him on the basis of principles contained in illustration (g) of Section 114 of the
Evidence Act. As seen from the facts of the decision relied upon by the learned Senior counsel for plaintiff in a suit filed by
Respondent No.1 for recovery of a sum of Rs.7000/- together with damages (Rs.1400) in the trial court which was dismissed as against him, but was decreed against the 2nd Respondent who, incidentally, also in the natural father of 1st Respondent who was subsequently adopted by his maternal grandfather”. As seen from the facts of the decision relied upon by the counsel for plaintiff are different to the facts of the present suit.
17.The learned Senior Counsel for plaintiff in order to substantiate his contention also relied upon another decision of the Hon’ble High Court of
Himachal Pradesh reported in AIR 2002 HP pg. 166, in a case between
RANJANA NAGPAL ALIAS RANJANA MALIK Vs. DEVI RAM AND
OTHERS, wherein His Lordship of the Hon’ble High Court of Himachal Pradesh in para 48 of the judgment by relying upon the judgment of the Hon’ble Supreme
Court reported in AIR 1999 SC pg 1341, held that:
22 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) “ If a defendant does not enter the witness box to make a statement on oath in support of the pleadings set out in the written statement, an adverse inference would arise that what he had stated in the written statement was not correct”.
There is no dispute with regard to the proposition of law as laid down by the
Hon’ble Supreme Court in the above said decision reported in AIR 1999 SC pg.
1341. As seen from the record, admittedly, the defendants mainly relied upon the admissions made by PW1 in his cross-examination. In a suit filed by the plaintiff for specific performance by way of mandatory injunction, the initial burden lies upon him to establish his case and he cannot depend on the weakness of the defendants case irrespective of the fact whether the defendants adduced their evidence or not. This Court is of the opinion that merely because the defendants 1 & 2 did not adduce any oral evidence it cannot be said that the case of the plaintiff is proved.
18.The learned Senior Counsel for defendants 1 & 2 submits that there is a breach of contract on the part of the plaintiff as the plaintiff did not develop the layout within one year from the date of approval. The learned counsel for defendants 1 & 2 further argued that the plaintiff failed to adhere to the time factor committing breach of essential term of the contract. On the other hand, the learned
Senior Counsel for plaintiff submits that in the absence of specific time stipulation in Exs.A1 & A2, the concept of reasonable time comes into play upon the facts and circumstances of each case. The learned Senior Counsel for plaintiff further argued that there was no delay on the part of the plaintiff in completing the physical aspect of the development of layout and there is no breach at all.
19. In view of the submissions made by the respective Senior Counsel of both parties, as seen from the recitals of Exs. A1 & A2 original Development 23 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Agreements dated 22-02-2007 and 27-05-2007, it is evident that the layout shall be completed as per Visakhapatnam Urban Development Authority norms.
Admittedly, Ex.A1 original Development Agreement dated 22-02-2007 does not contain any time stipulation for performance of contract. Section 46 of the Indian
Contract Act stipulates that if no time is stipulated for performance of contract, it shall be completed within a reasonable time. As seen from the cross-examination of PW1 who is the plaintiff in this case he categorically admitted that fixation of one year period by the Visakhapatnam Urban Development Authority is one of the norms of Visakhapatnam Urban Development Authority. PW1 himself admitted that contract of this nature covered by Ex.A2 will have time stipulations. As per clause (1) of Ex.A1 Development Agreement dated 22-02-2007, the plaintiff agreed to develop the land of D1 & D2 into a layout of residential plots. As seen from the contents of Ex.A4 the time given is one year from the date of approval.
The main contention of the plaintiff is that after approval of the layout on 05-01-2008 the 1st defendant did not allow him to carryout development work on the ground of auspicious days for laying foundation. The learned Senior Counsel for plaintiff submits that except for laying out BT roads the plaintiff has completed all other works in the year 2009 itself. In view of the submission made by the learned Senior Counsel for plaintiff, as seen from the cross-examination of
PW1 who is the plaintiff in this suit, he categorically admitted that the development of the land means developing the land by laying roads, providing electricity, arranging open spaces, arranging avenue plantation, completing plotting work, arranging drains, water facility as per Visakhapatnam Urban
Development Authority norms. PW1 further admitted in his cross-examination that as per the time fixed by the Visakhapatnam Urban Development Authority he supposed to complete the above works within one year. PW1 further admitted in 24 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) his cross-examination that the defendants 1 & 2 have cooperated with him in corresponding with Visakhapatnam Urban Development Authority in the issues of the actual physical development of the land. PW1 further admitted in his cross- examination that he did not lay the BT roads till six months prior to March, 2011.
PW1 further admitted in his cross-examination that the period of one year given for development while approving plan was over by the time of Ex.A37 i.e., copy of the G.O.Ms.No. 276 dated 02-07-2010. Admittedly, the plaintiff got issued a legal notice under the original of Ex.A18 dated 18-08-2011 to the defendants 1 to 3 and the defendants 1 to 3 received the same under Exs.A19 to A21 postal acknowledgments. After receipt of the original Ex.A18, the 3rd defendant got issued a reply on 16-09-2011 under Ex.A22. There is no dispute that the plaintiff got issued final legal notice to the defendants on 18-05-2012 under the original of
Ex.A23 and the defendants 1 to 3 received the same under Exs. A24 to A26 postal acknowledgments. Subsequently, the plaintiff got issued addendum to the final legal notice under the original of Ex.A27 to the defendants 1 to 3 and the defendants 1 to 3 received the said addendum under Exs. A28 to A30 postal acknowledgments. The law is well settled that if there is no time period specified for the performance of the contract and the promisor has to perform the contract without any request by the promisee, in such a case a promisor must perform the contract within a reasonable time. The reasonableness or unreasonableness of time used or taken by a party may be the subject of judicial review in light of the nature, purpose and circumstances of each case. In considering whether there has been unreasonable delay in performance, a court may also consider other factors such as prior dealings between the parties, business routine or customs within the trade, and whether there were any objective manifestations of expectation expressed between the parties.
25 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
20.As seen from the record it is evident that the defendants 1 & 2 alleges three short comings in the layout i.e., (1) approaching road (2) drains and (3) plots being below the road level. As per EX.A4 proceedings an approach road with standard road specifications shall be arranged. As per the specifications of Visakhapatnam
Urban Development Authority drains shall be of R.R masonry and they shall have a depth of three feet and the width of three feet and some of the plots in the layout are below the road level. In order to substantiate the case of the plaintiff, the learned Senior Counsel for plaintiff submits that the plaintiff had developed the layout as per the norms of the Visakhapatnam Urban Development Authority and the same is supported by the report submitted by the Advocate Commissioner. In view of the submission made by the learned Senior Counsel for plaintiff, as seen from the record admittedly an Advocate Commissioner was appointed in
I.A.2627/2015 filed by the plaintiff to carryout local inspection of the layout and to report whether or not there is violation of the approved plan. The learned Advocate
Commissioner made a local inspection of the layout and submitted his report. The main contention of the plaintiff is that as per the report submitted by the Advocate
Commissioner it is clear that the developer i.e., the plaintiff has developed the layout in accordance with the conditions of sanction and there is no breach at all.
On the other hand, the learned counsel for defendants 1 & 2 submits that the plaintiff did not arrange approach road to the layout with standard specifications so far and the drains and as per the specifications of Visakhapatnam Urban
Development Authority, drains shall be of R.R Masonry. The learned Advocate
Commissioner had deliberately given a false report that the drains of R.R Masonry were arranged. In view of the submissions made by the respective Senior Counsel of both parties, as seen from the record admittedly, the plaintiff did not examine the learned Advocate Commissioner as a witness and the report submitted by the 26 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) learned Advocate Commissioner was not marked as exhibit. The learned Senior
Counsel for plaintiff submits that the report submitted by the Advocate
Commissioner shall form part of the record and the said report shall be taken into consideration as per order XXVI Rule 10(2) of the Code of Civil Procedure. On the other hand, the learned counsel for defendants 1 & 2 submits that without examining the Advocate Commissioner and without marking the report submitted by the Advocate Commissioner the contents of the report cannot be taken into consideration. In view of the submissions made by the respective counsel of both parties, it is necessary to define Order XXVI Rule 10(2) of the Code of Civil
Procedure:
“The report of the Commissioner and the evidence taken by him (but not the evidence without the report) shall be evidence in the suit and shall form part of the record; but the Court or, with the permission of the Court, any of the parties to the suit may examine the Commissioner personally in open Court touching any of the matters referred to him or mentioned in his report, or as to his report, or as to the manner in which he has made the investigation”.
21.The law is well settled that the report submitted by the Advocate
Commissioner in the suit forms part of the record. The report of the Commissioner has therefore, evidentiary value and can be utilised by either of the parties as evidence in support of their case. In the present suit, admittedly, the plaintiff did not examine the Advocate Commissioner who submitted his report as a witness for the reasons best known to the plaintiff. As seen from the report submitted by the Advocate Commissioner in the Annexure attached to the Commissioner report there is absolutely no reference about the approach road. Right from the beginning the case of the defendants 1 & 2 that the drains were not arranged with R.R.
27 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Masonry and that they were arranged with fly ash bricks and that the drains are only of 1x 3 three feet. As seen from the report submitted by the Commissioner, he categorically noted that the drains of R.R Masonry were arranged. The learned counsel for defendants 1 & 2 submits that the Commissioner has deliberately given a false report that the drains were arranged. In order to substantiate his contention the learned counsel for defendants 1 & 2 mainly relied upon the admissions made by PW1 who is plaintiff in the suit in his cross-examination. As seen from the cross-examination of PW1 he categorically admitted that the drains were not made with R.R. Masonry. PW1 further stated in his cross-examination that the drains were made of fly ash bricks as R.R Masonry was not available.
22.The learned Senior Counsel for plaintiff submits that the period of one year stipulated in Ex.A4 proceedings dated 05-01-2008 was not pragmatic and was unrealistic. The learned Senior Counsel for plaintiff further argued that the
Government of Andhra Pradesh in G.O.Ms.No. 276 dated 02-07-2010 increased the time for development from one year to three years. He further argued that there was no delay on the part of the plaintiff in completing the physical aspects of the layout.
23.On the other hand, the learned counsel for defendants 1 & 2 submits that the
G.O.Ms.No. 276 relied upon by the plaintiff is prospective in nature and not retrospective in nature and cannot be made applicable to all layouts whose initial period of one year time for completion is over by the date of the said G.O. In view of the submissions made by the respective Senior Counsel of both parties, as seen from the record the plaintiff mainly relied upon Ex.A37 i.e., copy of
G.O.Ms.No.276 dated 02-07-2010. As seen from the contents of Ex.A37 the
Government of Andhra Pradesh, Municipal Administration and Establishment 28 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Development Department in G.O.Ms.No.276 dated 02-07-2010 considering the representations received from various organisations to increase the period for development of layout from one year to three years is extended the period of layout is increased from one year to three years. The plaintiff also addressed a letter under the original of Ex.A40 to the Visakhapatnam Urban Development Authority dated 12-07-2011 seeking extension of time along with payments. Ex.A41 relied upon by the plaintiff is the original receipt issued by the Visakhapatnam Urban
Development Authority dated 16-07-2011. In pursuance of the letter addressed by the 1st defendant under the original of Ex.A40 and basing upon the G.O issued by the Government of Andhra Pradesh under Ex.A37 the Visakhapatnam Urban
Development Authority issued proceedings under the original of Ex.A42 i.e., true copy of the order dated 08-11-2011 extending time upto 04-01-2012. The main contention of the learned Senior Counsel for defendants 1 & 2 that the original of
Ex.A37 G.O issued by the Government of Andhra Pradesh is prospective in nature and not retrospective in nature and cannot be made applicable to all layouts whose initial period of one year time for completion is over by the date of said G.O. In view of the submission made by the learned Senior Counsel for defendants 1 & 2 as seen from the record, the subject layout was approved in the year 2008 with a stipulation that the layout shall be completed in one year. As seen from the documents filed by the plaintiff he sought for extension of time under the original of Ex.A40 for completion of the layout. Considering the submissions made by the respective Senior Counsel of both parties and in view of the admissions made by
PW1 in his cross-examination this Court is of the opinion that the plaintiff failed to adhere to the time factor for completion of the layout.
24.The learned Senior Counsel for plaintiff submits that time is not essence of the contract as Exs. A1 & A2 did not contain any time stipulation. On the other 29 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) hand, the learned Senior Counsel for defendants 1 & 2 submits that generally contracts of this nature covered by EX.A1 contain a stipulation about time for performance of contract irrespective of the fact whether parties have agreed time as essence of the contract or not. The learned counsel for defendants 1 & 2 further argued that if no time is stipulated in Ex.A1 for performance of contract it shall be completed within a reasonable time.
25.In view of the submissions made by the respective Senior Counsel of both parties, as seen from the contents of Ex.A1 Development Agreement dated 22-02-2007 no time is stipulated for performance of the contract. The legal position is clear from the decision of a constitution bench of the Hon’ble Supreme
Court in CHAND RANI VS KAMAL RANI, reported in 1993(1) SCC pg.519, wherein their Lordships of the Hon’ble Supreme Court held that:
“It is a well-accepted principle that in the case of sale of immovable property, time is never regarded as the essence of the contract. In fact, there is presumption against time being the essence of the contract. This principle is not in any way different from that obtainable in England. Under the law of equity which governs the rights of the parties in the case of specific performance of contract to sell real estate, law looks not at the letter but at the substance of the agreement. It has to be ascertained whether under the terms of the contract the parties named a specific time within which completion was to take place, really and in substance it was intended that it should be completed within a reasonable time. An intention to make time the essence of the contract must be expressed in unequivocal language.
In the present case even though no time is stipulated for completion of the layout as per the terms of EX.A1, This Court may infer that it is to be performed in a reasonable time i.e., (i) from the express terms of the contract (ii) from the nature 30 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) of the property (iii) from surrounding circumstances, per example, the object of making the contract. The intention to treat time is the essence of the contract may however be evidenced by circumstances which are sufficiently strong to displace the normal presumption that time is not essence in contract. As seen from the cross-examination of PW1 who is the plaintiff in the suit, he categorically admitted that EXs.A1 and A2 are reciprocal agreements. PW1 further admitted in his cross- examination at page No.5 that he has taken extension of time thrice i.e., six months, six months and one year apart from the three years period that the
Government had given to every developer. PW1 further admitted in his cross- examination that the period of one year given for development while approving plan was over by the time of Ex.A37 G.O. He further admitted in his cross- examination that as per Exs.A1 & A2 Agreements he has to develop the land as per
Visakhapatnam Urban Development Authority norms.
26.The learned Senior Counsel for defendants 1 & 2 submits that the plaintiff had violated the essential conditions of the contract by transferring of the contract to Satya Construction a partnership firm without prior written permission of defendants 1 & 2. The learned Senior Counsel for defendants 1& 2 further argued that the plaintiff has committed breach of contract by transferring the contract to a partnership firm by violating clause-14 of Ex.A1 Agreement. On the other hand, the learned Senior Counsel for plaintiff submits that the assignment of contract presupposes the extinguishment of contractual relationship between the original parties to the contract and substitution of different set of parties and assumption of jural relationship by such substituted parties. The learned counsel for plaintiff further argued that there is no such extinguishment of jural relationship between the original parties to the contract. The learned Senior Counsel for plaintiff further argued that the relationship between the partners inter see is of no concern to the 31 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) defendants nor has it any impact on the development agreements. The learned
Senior Counsel for plaintiff further argued that there is no pleading in the written statement regarding the alleged assignment of contract under Ex.A1 to Satya
Constructions without permission of defendants 1 & 2. He further argued that the defendants 1 & 2 are estopped from contending that the alleged transfer took place without the consent of the defendants 1 & 2.
27.In view of the submissions made by the respective Senior Counsel of both parties, as seen from the contents of Ex.A1 Development Agreement dated 22-02- 2007 as per clause14 of Ex.A1 the developer shall not transfer or assign the contract to any other person without prior written permission of the owners.
Admittedly, the plaintiff had violated clause-14 of Ex.A1 Agreement by transferring of the contract to Satya Constructions a partnership firm without written permission of defendants 1 & 2. As seen from the cross-examination of
PW1 who is the plaintiff in this suit he categorically admitted at page No.6 of his cross-examination that this project which is the subject matter of the suit at the beginning was in his individual name later it became transaction of firm called
Satya Constructions. PW1 further admitted in his cross-examination at page No.6 that it is true Satya Constructions is not a party in this suit as there are four partners in Satya Constructions and it is a registered partnership firm. PW1 further admitted in his cross-examination that from 1st April, 2008 onwards the transaction under
Ex.A1 & A2 had gone from his individual name to the firm. PW1 further admitted in his cross-examination that from 1st April, 2008 onwards the firm shall bare the profit and loss if any in the transactions covered by Exs.A1 & A2. PW1 further admitted in his cross-examination that the transaction covered under Ex.A1is between him and the defendants 1 & 2. He further admitted in his cross- examination at page No.6 that there is a clause in Ex.A1 he shall not transfer or 32 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) assign the contract to any other person without written permission from the owners. PW1 further admitted in his cross-examination that from the beginning the contract under Ex.A1 became the contract of Satya Constructions. PW1 further admitted in his cross-examination that he did not refer about Satya Constructions either in his pleadings or in his legal notice. He further admitted in his cross- examination that the entire extent for the layout from 1st April 2008 was on the account of Satya Constructions. PW1 who is plaintiff in the suit further admitted in his cross-examination that Satya Constructions firm was established for the purpose of this layout and the firm is continuing and not dissolved. PW1 further admitted in his cross-examination that he did not obtain any written permission from the defendants 1 & 2 to transfer the contract to Satya Constructions. In view of the specific admissions made by PW1 in his cross-examination this Court safely come to a conclusion that the plaintiff has committed breach of contract by transferring the contract to a partnership firm i.e., Satya Constructions by violating clause-14 of Ex.A1 Agreement. Admittedly, the plaintiff did not institute the suit against the defendants in the name of Satya Constructions and the said Satya
Constructions is not a party to the suit. The plaintiff filed the suit in his individual capacity but not in the name of Satya Constructions which is a partnership firm.
28.The learned Senior Counsel for plaintiff submits that without pleading in the written statement the admissions made by PW1 cannot be considered. In order to substantiate his contention the learned Senior Counsel for plaintiff mainly relied upon Exs. A6 to A16 certified copies of Sale Deeds and Ex.A17 completion certificate dated 22-04-2009 issued by the Assistant Engineer operation Section
APEPDCL dated 22-04-2009. The main contention of the learned counsel for plaintiff is that in Exs. A9 to A15 sale deeds there is a clear recital that Satya
Constructions was the recipient of sale consideration as such the defendants 1 & 2 33 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) are estopped from contending that the alleged transfer took place without the consent of the defendants 1 & 2. In view of the submission made by the learned
Senior Counsel for plaintiff, as seen from the contents of the written statement filed by the defendants 1 & 2 admittedly there is no pleading in the written statement about the alleged assignment of the contract under Ex.A1 to Satya
Constructions. This court is of the view that even assuming for argument sake that there is no pleading in the written statement about the alleged transfer of contract to Satya Constructions covered under Ex.A1, as seen from the averments of the plaint there is no whisper about the transfer of contract to Satya Constructions which is a partnership firm. As seen from the cross-examination of PW1 who is the plaintiff in this suit he categorically admitted that he did not refer about Satya
Constructions either in his pleadings or in his legal notice got issued to the defendants. PW1 further admitted in his cross-examination that Satya Construction firm was established for the purpose of this layout only. When there is no pleading in the plaint or in the legal notice got issued by the plaintiff to the defendants under the original of Ex.A18 the question of denial of such fact in the written statement by the defendants 1 & 2 does not arise. As such the contention of the learned Senor
Counsel for plaintiff that the defendants 1 & 2 are estopped from contending that the alleged transfer of contract to Satya Construction without prior written permission of defendants 1 & 2 is not tenable. It is not the case of the plaintiff that
Satya Construction is no way concerned with regard to the transaction covered under Ex.A1. The learned Senior Counsel for plaintiff submits that mere fact that the plaintiff became the partner of Satya Construction and the developmental work was got done through the said firm does not mean that it is the extinguishment of rights and obligations of the plaintiff as well as the defendants 1 &2. In view of the submission made by the learned Senior Counsel for plaintiff, as seen from the 34 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) cross-examination of PW1 who is the plaintiff in this suit he categorically admitted that Satya Construction firm was established for the purpose of this layout only and the said firm is continuing and not dissolved. PW1 further admitted in his cross- examination that the firm had paid Rs. 22,92,750/- (Rupees Twenty Two Lakhs
Ninety Two thousand and Seven Hundred Fifty only) towards land conversion charges. This Court is of the opinion that when a contract covered under Ex.A1 was transferred to Satya Construction as admitted by PW1 in his cross-examination the suitor shall be Satya Constructions and it shall in force the contract and not the plaintiff in his individual capacity. In order to substantiate the case of the defendants 1 & 2, the learned Senior Counsel for defendants 1 & 2 relied upon a decision of the Hon’ble Supreme Court in a case between KAPILABEN VS
ASHOK KUMAR JAYANTILAL SHETH decided in Civil Appeal No.10683- 86/2014 dated 25-11-2019, wherein Their Lordships of the Hon’ble Supreme Court held that:
“It was the intention of the parties to any contract that any promise contained in it should be performed by the promisor himself, such promise must be performed by the promisor. In other cases, the promisor or his representative may employ a competent person to perform it.” It is clear from the above that the promisor ‘may employ a competent person’, or assign the contract to a third party as the case may be, to perform the promise only if the parties did not intend that the promisor himself must perform it. Hence in a case where the contract is of personal nature, the promisor must necessarily show that the promisee was agreeable to performance of the contract by a third person/assignee, so as to claim exemption from the condition specified in Section 40 of the Contract Act. If the promisee’s consent is not obtained, the assignee cannot seek specific performance of the contract”.
35 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
In the present case it is not the case of the plaintiff that he obtained the consent of either oral or written from the defendants 1 & 2 in respect of transfer of contract covered under Ex.A1 to Satya Constructions. Hence, this Court not inclined to accept the contention of the learned Senior Counsel for plaintiff.
29.The learned Senior Counsel for plaintiff submits that evasive denial of allegation of fact is of no denial at all and that the same shall be taken as admitted.
In order to substantiate the contention of the learned counsel for plaintiff he mainly relied upon Ex.A3 original approved layout plan and Ex.A4 true copy of the proceedings dated 05-01-2008. As seen from the contents of the written statement filed by the defendants 1 & 2 they took a specific plea that they never denied perform their part of the contract and the plaintiff has not satisfied the conditions of the approval accorded by the Visakhapatnam Urban Development Authority for development of the layout, thereby violated his part of the contract. In order to substantiate the case of the plaintiff, the learned Senior Counsel for plaintiff relied upon a decision of the Hon’ble Supreme Court reported in AIR 1964 SC pg.318, in a case between BADAT AND COMPANY Vs. EAST INDIA TRADING
COMPANY, wherein their Lordships of the Hon’ble Supreme Court in para 32 of the judgment held that:
“The written statement must deal specifically with each allegation of fact in the plaint and when a defendant denies any such fact, he must not specific do so evasively, but answer the point of substance. If his denial of a fact is not specific but evasive, the said fact shall be taken to be admitted”.
In the present case as seen from the contents of the written statement filed by the defendants 1 & 2 they have specifically denied each and every pleading of the plaint.
36 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
30.The learned Senior Counsel for plaintiff submits that the defendants did not perform their obligations even though the plaintiff was ready and willing to perform his part of the contract. On the other hand, the learned Senior Counsel for defendants submits that the plaintiff failed to perform his part of contract as per terms and conditions of Ex.A1 Development Agreement dated 22-02-2007 even though the defendants are ready and willing to perform their part of contract.
31.In view of the submissions made by the respective Senior Counsel of both parties, the law is well settled that in a suit for specific performance the plaintiff should plead and prove that he is always ready and willing to perform his part of contract. Mere taking a plea in the plaint is not sufficient. The plaintiff must prove with cogent evidence his readiness and willingness to perform his part of contract at all material times i.e., from the date of contract till the date of suit. The relief of specific performance is an equitable relief and it is within the discretion of the
Court.
The relief of specific performance is discretionary and it should not be granted merely because it is lawful to do so but it is governed by sound judicial principles. The grant of relief is the discretion of the Court and cannot be claimed as a matter of right. But however, the discretion shall not be arbitrary; it should be governed by rules and principles.This Court already discussed in detail and came to a conclusion that the plaintiff failed to perform his part of contract covered under Ex.A1. Hence, this Court not inclined to accept the contention of the learned
Senior Counsel for plaintiff. Accordingly, these issues 1 to 4 are decided in favour of the defendants and against the plaintiff.
37 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
32.Issues 5 & 6:
Issue No. 5: Whether the suit is maintainable for the relief of mandatory injunction to execute Gift deed, if so, is the plaintiff entitled to the relief of mandatory injunction for execution of Gift deed by the defendants?
Issue No.6: Whether the suit is maintainable for the relief of mandatory injunction to direct the defendants to obtain release of mortgaged plots and if so, is the plaintiff entitled for the said relief of mandatory injunction?
So far as these two issues are concerned, the burden lies on the plaintiff as the plaintiff filed the suit for mandatory injunction against the defendants to execute and register the Gift Deed in favour of Kapuluppada Panchayat,
Bheemunipatnam Mandal represented by its Secretary in respect of open spaces etc., of approved layout No.1/2008 and to execute necessary papers and documents so as to obtain release of plots 16 to 34, 84 to 91 of approved layout 1/2008 mortgaged in favour of Visakhapatnam Urban Development Authority at the costs and expenses of the plaintiff.
33.The learned Senior Counsel for plaintiff submits that several times the plaintiff requested the defendants to register the Gift Deed in favour of
Kapuluppada Gram Panchayat and obtain release of mortgaged plots at the expenses of the plaintiff but the defendants 1 & 2 have been postponing the same on one pretext or other, even though the 3rd defendant has agreed to the terms and conditions of Ex.A4 approved plan. The learned Senior Counsel for plaintiff further submits that the plaintiff got issued a legal notice to the defendants to execute and register the Gift Settlement Deed in favour of Kapuluppada Gram
Panchayat at the costs and expenses of the plaintiff and thereafter to execute necessary documents as and when the Visakhapatnam Urban Development
Authority releases the mortgaged plots and the defendants 1 to 3 received the said notice and the 3rd defendant gave a reply stating that he is ready and willing to sign the necessary documents but the defendants 1 & 2 did not give any reply. The 38 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) learned Senior Counsel for plaintiff further argued that due to latches on the part of the defendants 1 & 2 to execute and register the Gift Settlement Deed infavour of
Kapuluppada Gram Panchayat the release of mortgage plots by Visakhapatnam
Urban Development Authority could not obtain. The learned Senior Counsel for plaintiff further argued that as the defendants 1 & 2 failed to execute Gift
Settlement Deed in favour of Kapuluppada Gram Panchayat the plots mortgaged to
Visakhapatnam Urban Development to ensure compliance with the conditions of approval will be released from mortgage. Hence, he prays the Court to direct the defendants to execute and register Gift Settlement Deed in favour of Kapuluppada
Grampanchayat to obtain release of plots mortgaged to Visakhapatnam Urban
Development Authority.
34.On the other hand, the learned Senior Counsel for defendants 1 & 2 submits that the execution of the Gift Settlement Deed in favour of Kapuluppada Gram
Panchayat for the mortgaged plots has not arisen because those mortgaged plots are still under mortgage and this Court would not create interest in an immovable property by way of decree when there is subsisting interest of somebody else in some of the properties. The learned Senior Counsel for defendants further argued that as the plaintiff could not comply with the legal formalities as contemplated under Ex.A4 approved layout as such the plaintiff is not entitled to seek the mandatory injunction by directing the defendants to execute a registered Gift
Settlement Deed in favour of Kapuluppada Gram Panchayat for release of plots mortgaged to the Visakhapatnam Urban Development Authority. The learned
Senior Counsel for defendants 1 & 2 further argued that the plaintiff is not entitled to seek the relief of mandatory injunction as prayed for as he did not approach the
Court with clean hands and true facts. The learned Senior Counsel for defendants further argued that the plaintiff has not so far developed the layout as per the 39 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) conditions and specifications of Visakhapatnam Urban Development norms and not paid the requisite amounts payable to the competent Authority and the plaintiff has not completed part of contract in terms of Development Agreement as such he is not entitled to seek the relief of mandatory injunction as prayed for. Hence, he prays the court to dismiss the suit with costs.
35.In view of the submissions made by the respective Senior Counsel of both parties, this Court is of the opinion that when the plaintiff seeks a relief of mandatory injunction the burden lies upon him to establish the same by adducing legal and documentary evidence and the plaintiff cannot depend upon the weakness of the defendants case. In order to establish the case of the plaintiff as seen from the chief evidence affidavit of PW1 he categorically stated that he has been repeatedly requesting the defendants to register the Gift Settlement Deed in favour of Kapuluppada Gram Panchayat and obtain release of mortgaged plots at his cost and expenditure but the defendants have been postponing the same on one pretext or other. PW1 further stated in his evidence that he got issued a legal notice under the original of Ex.A18 to the defendants 1 to 3 and the defendants 1 to 3 received the same under Exs.A19 to Ex.A21 postal acknowledgments and the 3rd defendant gave a reply under Ex.A22 but the defendants 1 & 2 did not give any reply. PW1 further stated in his chief evidence that again he got issued another legal notice under the original of Ex.A23 to all the defendants and all the defendants received the said notice under Ex.A24 to A26 postal acknowledgments. He further stated in his evidence that as there was an omission certain plot numbers registerable to him, he got issued an addendum under the original of Ex.A27 and the defendants 1 to 3 received the same under Exs. A28 to A30 postal acknowledgments. As seen from conditions incorporated in Ex.A4 permission for approval of layout, condition
No.6 speaks that the deed of mortgage executed by the applicant in favour of 40 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Visakhapatnam Urban Development Authority is purely a measure to ensure compliance of the conditions of Development of infrastructure by the applicant/developer and the Visakhapatnam Urban Development Authority is no way accountable to the plots registered in the event of default by the applicant/developer. As per conditions No.9 of Ex.A4 of the layout, the applicant is directed to complete the above developmental works within a period of one year and submit a requisition letter for releasing of mortgage plots/area, which is in favour of Vice Chairman, Visakhapatnam Urban Development Authority duly enclosing letter in regard to roads, open spaces taken over by the Panchayat
Secretary, Kapuluppada Gram Panchayat. As per conditions No.12 of Ex.A14 the local authority, shall not approve and release any subject permission or allow any prior permission in the area under mortgaged to the Visakhapatnam Urban
Development Authority in particular and in other plots of the layout in general until and unless the applicant has completed the developmental works and then got release the mortgaged land from the Visakhapatnam Urban Development
Authority.
36. The learned Senior Counsel for defendants submits that the plaintiff could not complete with these legal formalities as the defendants did not come forward to execute the register Gift Settlement Deed and thereafter to execute necessary papers to obtain release of mortgaged plots. On the other hand, the learned Senior
Counsel for defendants 1 & 2 submits that as the plaintiff did not comply with the terms and conditions incorporated in Ex.A4 as such the plaintiff is not entitled to seek the relief of mandatory injunction.
37.In view of the submission made by the respective Senior Counsel of both parties, as seen from the cross-examination of PW1 who is the plaintiff in this suit, 41 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) he categorically admitted at page No.5 of his cross-examination that as per Exs.A1 and A2 Development Agreements he has to develop the land as per the
Visakhapatnam Urban Development Authority norms. PW1 further admitted in his cross-examination that the Visakhapatnam Urban Development Authority norms include the time fixed by Visakhapatnam Urban Development Authority for completion of the project. PW1 further admitted in his cross-examination that as per the time fixed by Visakhapatnam Urban Development Authority he has supposed to complete the above works within one year. He further admitted in his cross-examination that the defendants 1 & 2 have no role at all what so ever in the above physical aspects of the layout. PW1 further admitted in his cross- examination that the defendants 1 & 2 are cooperating him in corresponding with
Visakhapatnam Urban Development in the issues of the actual physical development of the land. Under Transfer of Property Act, mortgage is one of the modes of transfer of interest in an immovable property. As seen from the conditions contemplated in Ex.A4 it is evident that the Visakhapatnam Urban
Development Authority would release mortgage only in case the layout is completed in all respects as per its specifications. Admittedly, both parties have agreed to earmark the plots only after layout is completed. As per condition No.12 of Ex.A4 the local authority will not approve or release any building permission until and unless the developmental works are completed and the mortgaged plots are released. Ex.A31 relied upon by the plaintiff is the true copy of the demand notice issued by the Revenue Divisional Officer to the defendants demanding payment of Rs. 15,28,500/- (Rupees Fifteen Lakhs Twenty Eight thousand and five hundred only) + 50% penalty dated 24-06-2008. After receipt of the original of
Ex.A31 the 1st defendant got issued a reply under the original of Ex.A32 dated 04-07-2009. Ex.A39 is the copy of the order of Thasildar, Bheemunipatnam dated 42 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) 06-03-2010 directing the defendants to pay Rs. 15,28,500/- (Rupees Fifteen Lakhs
Twenty Eight thousand five hundred only) + 50% penalty after receipt of the said order under Ex.A33, the 1st defendant got issued a reply dated 21-03-2010 in pursuance of the order passed by the Tahsildar. EX.A35 is the Xerox copy of the letter dated 02-11-2012 addressed by the Visakhapatnam Urban Development
Authority to 3rd party insisting upon payment of NALA before releasing the mortgaged plots. Ex.A36 is the copy of the proceedings of the Revenue Divisional
Officer dated 07-01-2013 granting permission for conversion and the same is marked after comparing with the original. Ex.A39 and A41 are the original receipts issued by the Visakhapatnam Urban Development Authority in respect of the payment of the amount. As seen from the record admittedly, the plaintiff submitted an application under the original of Ex.A43 dated 19-01-2019 to the authorities of
Visakhapatnam Urban Development Authority for renewal of layout. Subsequent to the filing of the suit the authorities of Visakhapatnam Urban Development
Authority issued a show cause notice dated 17-11-2012 to the defendants under the original of Ex.A.45. Ex.A.45 relied upon by the plaintiff is the true copy of the show cause notice dated 17-11-2012 issued by the Visakhapatnam Urban
Development Authority as to why the layout permission should not be cancelled and mortgaged plots be sold within 15 days from the date of its receipt. After receipt of the original of Ex.A45 the 1st defendant got issued a reply under Ex.A46
dated 04-12-2012. Again the Visakhapatnam Urban Development Authority got
issued a show cause notice to the 1st defendant under original of Ex.A47 dated 13-05-2013 and after receipt of the same the 1st defendant got issued a reply under the original of Ex.A48 dated 18-05-2013 along with enclosures. Ex.A49 is the letter addressed by the Visakhapatnam Urban Development Authority to the 1st defendant with a request for release of mortgaged plots by paying an amount of 43 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Rs. 1,23,655/- (Rupees One Lakh Twenty three thousand Six hundred Fifty five only) towards penalty charges. After receipt of the original of Ex.A49 the 1st defendant got issued a reply under the original of Ex.A50. Ex.A51 is the receipt issued by Visakhapatnam Urban Development Authority in respect of payment of an amount of Rs. 1,23,655/- (Rupees One Lakhs Twenty three thousand Six hundred Fifty five only) by the 1st defendant. Ex.A52 is the information given by the Visakhapatnam Urban Development Authority to the plaintiff under Right to
Information Act. Right from the beginning the case of the defendants 1 & 2 is that the plaintiff did not approach the Court with clean hands and true facts as such he is not entitled to seek the relief of mandatory injunction by directing the defendants to execute a register Gift Deed in favour of Kapuluppada Gram Panchayat for release of mortgaged plots. In view of the submission made by the learned Senior
Counsel for defendants 1 & 2, the law is well settled that a person who seeks the relief of specific performance by way of mandatory injunction must come to the
Court with clean hands and true facts since the relief itself is a discretionary relief.
This Court is of the opinion that in the present suit the plaintiff did not approach the Court seeking the relief of mandatory injunction with clean hands and true facts as such he is not entitled to seek the said relief. Accordingly these issues 5 & 6 are decided in favour of the defendants and against the plaintiff.
38.Issue No.7: Is this suit as framed is maintainable?
So far as this issue is concerned this Court already discussed in detail while answering issues 1 to 4 and came to a conclusion that the plaintiff has committed breach of contract by transferring the contract to a partnership firm i.e., Satya
Construction by violating clause-14 of Ex.A1 Agreement and PW1 also admitted the said aspect in his cross-examination. This Court is of the opinion that when 44 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Ex.A1 contract was transferred to Satya Constructions the suitor shall be Satya
Constructions and it shall enforce the contract but not the plaintiff. The plaintiff individually cannot get benefit if any in this suit. As seen from the cross- examination of PW1 who is plaintiff in the suit he categorically admitted that Satya
Construction firm was established for the purpose of this layout only. He further admitted in his cross-examination that the project which is the subject matter of the suit at the beginning was in his individual name later it became the transaction of
Firm called Satya Constructions. PW1 further admitted in his cross-examination that Satya Constructions is not a party to the suit. In view of the admissions made by PW1 in his cross-examination this Court without any hesitation come to a conclusion that the suit as framed by the plaintiff in his individual capacity is not maintainable. Accordingly, this issue is answered.
39. Issue No.8: Whether the plaintiff is entitled to the relief of specific performance as prayed for?
So far as this issue is concerned, the learned Senior Counsel for plaintiff submits that the plaintiff has performed his part of the contract and the defendants have not performed their part of contract despite several requests of the plaintiff.
The learned Senior Counsel for plaintiff further argued that the plaintiff who is the developer of the layout is entitled to the relief of Specific performance. The learned Senior Counsel for plaintiff further argued that even though the plaintiff was ready and willing to perform his part of contact, the defendants did not come forward to perform their part of contract as per the terms of Ex.A1 Development
Agreement. The learned Senior Counsel for plaintiff further argued that as the defendants 1 & 2 are refusing to register the plots in favour of the plaintiff or his nominees as such the plaintiff got issued a legal notice to the defendants demanding them for execution of Sale Deeds in favour of the plaintiff. The learned 45 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Senior Counsel for plaintiff lastly contended that the plaintiff has completed the development of the layout in all respects as such the plaintiff is entitled to seek specific performance as prayed for. Hence, he prays the Court to direct the defendants to execute a registered Sale Deed infavour of the plaintiff or his nominees in respect of the plaint schedule property.
40.On the other hand, the learned Senior Counsel for defendants 1 & 2 submits that the plaintiff has not developed the layout as per the conditions and specifications of Visakhapatnam Urban Development Authority norms as such the plaintiff is not entitled to seek the relief of specific performance as prayed for. The learned Senior Counsel for defendants 1 & 2 further argued that the plaintiff has failed to perform his part of contract and the plaintiff himself has not satisfied the conditions of the approval accorded by the VUDA for development of the lay out and thereby the plaintiff has violated his part of the contract. The learned Senior
Counsel for defendants 1 & 2 further argued that the defendants 1 & 2 are ready and willing to execute the documents in favour of the plaintiff provided the plaintiff proves that he has fulfilled all the conditions of Ex.A4. The learned Senior
Counsel for defendants 1 & 2 further argued that the plaintiff is not ready and willing to perform his part of contract as such he is not entitled to seek the relief of specific performance. The learned Senior Counsel for defendants 1 & 2 further argued that mere taking a plea in the plaint that the plaintiff was always ready and willing to perform his part of contract is not sufficient and the plaintiff must prove with cogent evidence his readiness and willingness to perform his part of the contract at all material times. The learned Senior Counsel for defendants 1 & 2 lastly contended that the relief of specific performance is an equitable relief and it is within the discretion of the court and the court is not bound to grant the relief 46 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) merely because there is a valid agreement. Hence, he prays the court to dismiss the suit with costs.
41.In view of the submissions made by the respective Senior Counsel of both parties the law is well settled that in a suit for specific performance, the plaintiff should plead and prove that he was always ready and willing to perform his part of contract. Mere taking a plea in the pliant is not sufficient. The plaintiff must prove with cogent evidence his readiness and willingness to perform his part of contract all material times i.e., from the date of the contract till the date of the suit. The relief of specific performance is an equitable relief and it is within the discretion of the Court.
42.In the present case in order to establish the case of the plaintiff as seen from the evidence affidavit of PW1 who is the plaintiff in the suit he categorically stated that he is always ready and willing to perform his part of contract but the defendants did not come forward to perform their part of contract. PW1 further stated in his evidence affidavit there was no delay in completion of obligations on his part. PW1 further stated in his evidence affidavit that he has been always ready and willing to perform his part of contractual obligations and he did not delay the development of the layout and the layout is developed to the satisfaction of
Visakhapatnam Urban Development Authority. PW1 further stated in his evidence that despite several requests made by him the defendants 1 & 2 did not come forward to perform their part of contract.
43.In view of the specific peal taken by the plaintiff the burden to establish that he has been always ready and willing to perform his part of the contract is on the plaintiff in a suit for specific performance. The aspect of readiness and willingness is to be decided taking into consideration the entirety of facts and circumstances relevant to the intention and the conduct of the parties. The plaintiff has to cover 47 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) and also to prove his readiness and willingness to perform his part of the contract in a suit for specific performance. Right from the beginning the case of the defendants 1 & 2 is that the plaintiff has committed breach of contract and there was no earmarking of plots and the plaintiff also approached this Court with unclean hands as such he is not entitled to seek the relief of specific performance as prayed for. In view of the specific plea taken by the defendants 1 & 2 it is no doubt true that as per Section 16(c) of the specific relief Act, 1963 readiness and willingness on the part of the plaintiff is a condition precedent for obtaining relief of grant of specific performance. It is also clear that in a suit for specific performance, the plaintiff must allege and prove continues readiness and willingness to perform the contract on his part from the date of the contract. The onus is on the plaintiff.
44.It is settled law that even in the absence of specific plea by the opposite party, it is the mandate of the statute that the plaintiff has to comply with Section 16(c) of the Specific Relief Act and when there is non-compliance with this statutory mandate, the court is not bound to grant specific performance and is left with no other alternative but to dismiss the suit. It is also clear that readiness to perform must be established throughout the relevant points of time. “Readiness and willingness to perform the part of the contract has to be determined/ascertained from the conduct of the parties.
45.The factum of readiness and willingness to perform the plaintiff’s part of the contract is to be adjudged with reference to the conduct of the party and the attending circumstances. The court may infer from the facts and circumstances whether the plaintiff was ready and was always ready and willing to perform his part of the contract. In the present case as seen from the terms and conditions of
Ex.A1 Development Agreement it is clear that the parties have agreed to earmark 48 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) the plots only after layout is completed. As seen from the averments of the plaint there is no whisper that after the entire layout is completed in all respects, he got the extent of plotted area in the layout. When the plaintiff sought for specific performance he shall necessarily establish the actual plotted area covered by the suit schedule plots and the plots which have been already sold to his nominees. As seen from the cross-examination of PW1 who is the plaintiff in the suit he categorically admitted as per terms and conditions of Exs A1 & A2 Development
Agreements he has to develop the land as per Visakhapatnam Urban Development
Authority norms. There is no dispute in between the parties with regard to execution of Exs. A1 & A2 Development Agreements. As seen from the contents of Ex.A1 Development Agreement dated 22-02-2007 as per condition No.6 the “owners shall register the plots allotted to the developer share of 15%(within the total 26%) in favour of the developer or his nominees/3rd parties after the completion of B.T Roads and drainages and the remaining 11% of share shall be registered after the completion of the entire project as per Visakhapatnam Urban
Development Authority norms. As per condition No.9 of Ex.A1 Development
Agreement dated 22-02-2007 after completion of development, the developer of the owners will earmark plot numbers in their ownership and the developer shall be entitled for 26% of plots and the land owners shall execute and register the regular
Sale Deed/deeds or other conveyance deed in favour of the developer/nominees of the developer and the developer shall have the right to enter into agreements, receive consideration, issue receipts there for, without having to account for the same, execute such deeds infavour of such 3rd parties. In the present case right from the beginning the case of the defendants that as the plaintiff failed to fulfil the conditions of Ex.A1 within stipulated time and did not approach the court with clean hands and true facts as such the plaintiff is not entitled to seek the relief of 49 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) specific performance. In view of the specific plea taken by the defendants, as seen from the cross-examination of PW1 who is the plaintiff in the suit, he categorically admitted that as per the time fixed by the Visakhapatnam Urban Development
Authority he was supposed to complete the above works within one year. PW1 further admitted in his cross-examination that as per Exs.A1 & A2 Development
Agreements he has to develop the lands as per Visakhapatnam Urban Development
Authority norms. Admittedly, the defendants 1 & 2 did not come to the witness box to say anything on oath. This Court is of the opinion that merely because the defendants 1 & 2 did not adduce any evidence to substantiate their contention, the
Court is not supposed to grant the relief of specific performance as sought by the plaintiff unless and until the plaintiff establishes his readiness and willingness to perform his part of contract.
46.It is well settled that remedy for specific performance is an equitable remedy. The court while granting decree of specific performance exercises its discretionary jurisdiction. Section 20 of the Specific Relief Act specifically provides that the court’s discretion to grant decree of specific performance is discretionary but not arbitrary. Discretion must be exercised in accordance with sound and reasonable judicial principles.
47.The relief of specific performance is discretionary and it is not given merely because it is lawful to do so, but it is governed by sound judicial principles. The grant of the relief is the discretion of the court and cannot be claimed as a matter of right. But, however, the discretion shall not be arbitrary; it should be governed by
Rules and Principles. A person who seeks the relief of specific performance must come to the court with clean hands since the relief itself is a discretionary relief. In the present case as seen from the record it is clear that the plaintiff did not approach this Court seeking the relief of specific performance with clean hands 50 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) and true facts as such this Court not inclined to accept the contention of the learned
Senior Counsel for plaintiff. Accordingly this issue is answered in favour of the defendants and against the plaintiff.
48.Additional Issue No.1: Whether the plaintiff is entitled to the alternative relief of compensation of Rs. 2,72,47,320/- (Rupees Two Crores Seventy Two Lakhs Forty Seven Thousand Three hundred and twenty only)as prayed for?
So far as this issue is concerned, the learned Senior Counsel for plaintiff submits that as per Section 21 of the Specific Relief Act, 1963 the plaintiff is entitled to claim compensation as an alternative to specific performance. The learned Senior Counsel for plaintiff further argued that when there is no standard measure to ascertain the exact damages the plaintiff is entitled to claim compensation as an alternative relief basing on the market value of the property.
The learned Senior Counsel for plaintiff further argued that in the absence of standards measure of ascertainment of damages, compensation can be awarded basing on the market value of the property. The learned Senior Counsel for plaintiff further argued that if the court comes to a conclusion that the plaintiff is not entitled for the relief of specific performance the court has got discretion to award compensation to the plaintiff as an alternative relief as prayed by the plaintiff.
49.On the other hand, the learned Senior Counsel for defendants 1 & 2 submits that the plaintiff has committed breach of contract as such he is not entitled for alternative relief of compensation. The learned Senior Counsel for defendants 1 & 2 further argued that the plaintiff claiming the value of the property and not compensation. The learned Senior Counsel for defendants 1 & 2 further argued that the plaintiff is not entitled to seek the alternative relief of compensation as prayed for.
51 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
50.In view of the submissions made by the respective Senior Counsel of both parties it is necessary to define Section 21 of the Specific Relief Act, 1963.
21. Power to award compensation in certain cases.— (1) In a suit for specific performance of a contract, the plaintiff may also claim compensation for its breach, either in addition to, or in substitution of, such performance.
(2) If, in any such suit, the court decided that specific performance ought not to be granted, but that there is a contract between the parties which has been broken by the defendant, and that the plaintiff is entitled to compensation for that breach, it shall award him such compensation accordingly.
(3) If, in any such suit, the court decides that specific performance ought to be granted, but that it is not sufficient to satisfy the justice of the case, and that some compensation for breach of the contract should also be made to the plaintiff, it shall award him such compensation accordingly.
(4) In determining the amount of any compensation awarded under this section, the court shall be guided by the principles specified in section 73 of the Indian Contract Act, 1872.
(5) No compensation shall be awarded under this section unless the plaintiff has claimed such compensation in his plaint: Provided that where the plaintiff has not claimed any such compensation in the plaint, the court shall, at any stage of the proceeding, allow him to amend the plaint on such terms as may be just, for including a claim for such compensation. Explanation.— The circumstance that the contract has become incapable of specific performance does not preclude the court from exercising the jurisdiction conferred by this section.
Provided that where the plaintiff has not claimed any such compensation in the plaint, the court shall, at any stage of the proceeding, allow him to amend the plaint on such terms as may be just, for including a claim for such compensation.
As seen from the provision of Section 21 of the Specific Relief Act, it is clear that the plaintiff is entitled to seek compensation as an alternative relief if the contract was broken by the defendant. In the present case this court already discussed in detail while answering issues 1 to 4 and came to a conclusion that the plaintiff himself has committed breach of contract by transferring the contract to a partnership firm by violating clause 14 of Ex.A1 Development Agreement as such 52 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) the plaintiff is not entitled to seek compensation under Section 21 of the Specific
Relief Act, 1963 as prayed for.
51.In order to substantiate the case of the plaintiff, the learned Senior Counsel for plaintiff relied upon a decision of the Hon’ble High Court of Andhra Pradesh reported in 2012(4)ALD Pg.183, in a case between CHINTAKAYALA
SIVARAMAKRISHNA Vs. NADIMPALLI VENKATA RAMA RAJU AND
OTHERS, wherein their Lordships of the Hon’ble High Court of Andhra Pradesh in para 68 of the judgment held that:
“According to clause (i) of the explanation to Section 10 of the 1963 Act there is a rebuttable presumption which operates in favour of purchasers that in the case of breach of a contract to sell immovable property the same cannot be adequately relieved by compensation in money. The appellant failed to plead any circumstances to show how this presumption could be rebutted, even before the trial Court. As seen from the facts of the decision relied upon by the learned Senior
Counsel for plaintiff are different to the present case”.
52.The law is well settled that having regard to Section 21 of the Specific Relief
Act when the contract becomes impossible with no fault of the plaintiff, Section 21 of the Specific Relief Act enables the Court to award compensation in lieu and substitution of the specific performance. The plaintiff is entitled to claim the amount of compensation as an alternative relief in a suit for specific performance if there was no fault on the part of the plaintiff. Section 21 of the Specific Relief Act specifically says that where the contract for no fault of the plaintiff becomes impossible enable the award of compensation in lieu and substitution of the specific performance. In the present case this Court already discussed in detail and came to a conclusion that the plaintiff has committed breach of contract and failed to perform his part of contract within the stipulated period of time and did not 53 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) approach the Court with clean hands and true facts as such he is not entitled to seek the alternative relief of compensation as prayed for. Accordingly, this issue is answered.
53.Additional Issue No.2: Whether the suit is valued properly for the purpose of Court fee?
So far as this issue is concerned, except taking a plea in the written statement by the defendants 1 & 2 that the suit is not valued properly for the purpose of Court fee nothing was placed before this Court. As seen from the averments of the plaint, the plaintiff valued the suit for the purpose of Court fee under Section 39(e) of the
Andhra Pradesh Court fee and suits valuation Act, and paid an amount of
Rs. 2,75,148/- (Rupees Two Lakhs Seventy Five thousand One Hundred Forty
Eight only) towards Court fee. As seen from the cross-examination of PW1 who is the plaintiff in this suit even no suggestion was made by the counsel for defendants 1 & 2 that the suit is not properly valued for the purpose of Court fee. Hence, in the absence of any material it cannot be said that the suit is not valued properly for the purpose of court fee. Accordingly, this issue is answered.
54.Issue No.9: To what relief?
By virtue of above discussion and by virtue of various contentions urged by the respective Senior Counsel of both parties this Court is of the opinion that the plaintiff failed to perform his part of contract and he has committed breach of contract by transferring the Contract to a partnership firm by violating clause 14 of
Ex.A1 Agreement and did not approach the Court with clean hands and true facts as such the plaintiff is not entitled to seek the reliefs as prayed for and the suit filed by the plaintiff deserves to be dismissed.
54 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
55.In the result the suit filed by the plaintiff is dismissed. There shall be no order as to costs.
Dictated to the Personal Assistant, transcribed by her, corrected and pronounced by
me in the open court this the 13th day of June, 2022.
Sd/-XXX
Special Judge for trial and Disposal of
Commercial Disputes, Visakhapatnam.
APPENDIX OF EVIDENCE
WITNESS EXAMINED
Plaintiffs: Defendant PW1: Meka Atchuta Rama Rao NIL
No. of exhibits marked for
Plaintiff:
Ex.A1: Original Development Agreement dated 22-02-2007 between the plaintiff and defendants 1 & 2. Ex.A2: Original Development Agreement dated 27-05-2007 between the plaintiff and 3rd defendant. Ex.A3: Blue print original approved layout plan. Ex.A4: True Copy of proceedings No.RC.No.4188/07/L2, dated 05-01-2008 of the 4th Defendant approving the layout. Ex.A5: Certified copy of registered mortgage deed dated 28-12-2007 executed by the defendants in favour of VUDA. EX.A6: Certified copy of Sale deed executed by the defendants in favour of 3rd party dt.17.09.2008 bearing document No.3491/2008. EX.A7: Certified copy of Sale deed executed the defendants in favour of 3rd party
dt. 17.09.2008 bearing document No. 3492/2008.
Ex.A8: Certified copy of the Sale deed executed by the defendants in favour of 3rd party dt.17.09.2008 bearing document No.3493/2008. Ex.A9: Certified copy of the Sale deed executed by the defendants in favour of 3rd party dt. 10.11.2008 bearing document NO.3957/2008. Ex.A10: Certified copy of the Sale Deed executed by the defendants in favour of 3rd party dt.10.11.2008 bearing document No.3958/2008. Ex.A11: Certified copy of the Sale deed executed by the defendants in favour of 3rd party dt. 10.11.2008 bearing document No.3959/2008. EX.A12: Certified copy of the Sale deed executed by the defendants in favour of 3rd party dt. 10.11.2008 bearing document No.4045/2008. Ex.A13: Certified copy of the Sale deed executed by the defendants in favour of 3rd party dt.19.11.2008 bearing document NO.4045/2008. Ex.A14: Certified copy of the Sale deed executed by the defendants in favour of 3rd party dt.19.11.2008 bearing document No.4046/2008. Ex.A15: Certified copy of the Sale deed executed by the defendants in favour of 3rd party dt.19.11.2008, bearing document No.4047/2008. Ex.A16: Certified copy of the Sale Deed executed by the defendants in favour of 3rd party dt.13.04.2011 bearing document No.1113/2011. Ex.A17: Completion certificate dt.22.04.2009 issued by Assistant Engineer Operation section APEPDCL. Ex.A18: Office copy of Legal Notice dt.18.08.2011got issued by the plaintiff. Ex.A19: Postal acknowledgment of D1. Ex.A20: Postal acknowledgment of D2.
55 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Ex.A21: Postal acknowledgment of D3. Ex.A22: Reply notice got issued by D3 dt. 16.09.2011. Ex.A23: Office copy of final legal notice got issued by the plaintiff dt.18.05.2012. Ex.A24: Postal Acknowledgment of D1. Ex.A25: Postal Acknowledgment of D2. Ex.A26: Postal Acknowledgment of D3. Ex.A27: Office copy of addendum to the final notice got issued by the plaintiff dt.02.06.2012. Ex.A28: Postal Acknowledgment of D1. Ex.A29: Postal Acknowledgment of D2. Ex.A30: Postal Acknowledgment of D3. Ex.A31: True copy of the notice issued by R.D.O to the defendants demanding payment of Rs. 15,28,500/-+50% penalty dt.24.06.2008. Ex.A32: Office copy of reply dt.04.07.2009 given by the 1st defendant in pursuance of the notice received from the R.D.O. Ex.A33: Original order of Thasildar dated 06-03-2010 directing the defendants to pay Rs. 15,28,500/- (Rupees Fifteen Lakhs Twenty Eight thousand five hundred only) +50% penalty dt.06.03.2010. Ex.A34: Office copy of the reply given by the 1st Defedant dated 27.03.2010 in pursuance of the Order passed by the Thasildar. Ex.A35: Xerox True copy of the letter dated 02.11.2012 addressed by VUDA to 3rd party insisting upon payment of NALA before releasing the mortgaged plots. Ex.A36: Photostat copy of the proceedings of the R.D.O dated 07.01.2013 granting permission for conversion (copy compared with the original then only it is marked as Ex.A36). Ex.A37: Copy of the G.O.Ms.No.276 dated 02.07.2010. Ex.A38: Office copy of the letter dated 26.05.2011 addressed by the plaintiff to VUDA seeking extension of time along with payment. Ex.A39: Original receipt dated 30.05.2011 issued by VUDA. Ex.A40: Office copy of letter dated.12.07.2011 addressed by the 1st defendant to VUDA seeking extension of time along with payment. Ex.A41: Original receipt issued by VUDA dt. 16.07.2011. Ex.A42: True copy of order dated 08.11.2011 from VUDA extending time up to 04.01.2012. Ex.A43: Office copy of application dt.19.01.2012 submitted by the 1st defendant to VUDA for renewal of layout. Ex.A44: Receipt issued by VUDA dt. 30.01.2012. Ex.A45: True copy of show cause notice dated 17.11.2012 issued by VUDA. EX.A46: Office copy of reply dated 04-12-2012 given by the 1st defendant. Ex.A47: Copy of notice issued by VUDA dr.13.05.2013. Ex.A48: Office copy of reply dated 18.05.2013 got issued by the 1st defendant along with enclosures. Ex.A49: True copy of the letter issued VUDA dated 03.09.2013. Ex.A50: Office copy of reply dated 15.09.2013 got issued by the 1st defendant along with enclosures. Ex.A51: Receipt issued by VUDA dated 25.09.2013. Ex.A52; Letter issued by VUDA dt.03-10-2015 along with enclosures under Right to Information Act. DEFENDANTS: NIL Sd/-XXX Spl.Judge Commercial Court/VSP 56 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012)
Date of presentation:31.07.2012 Date of filing : 07.09.2012
IN THE HON’BLE COURT OF THE SPECIAL JUDGE FOR TRIAL AND DISPOSAL OF COMMERCIAL DISPUTES: VISAKHAPATNAM
Present: G. Vallabha Naidu
Special Judge for Trial and Disposal of
Commercial Disputes, Visakhapatnam. Monday, this the 13th day of June, 2022 COS. No.2 /2018 (Old O.S.No.389/2012) Between: Meka Atchuta Ramarao, aged 46 years, Businessman, son of Late Satyanarayana Murthy, resident of Flat No.204, Sampath Arcade, Narasimha Nagar, Visakhapatnam 530024. …. Plaintiff And:
1. Kakarlapudi Suryanarayana Raju, aged around 68 years, Hindu, S/o. Late Sambasiva Raju, resident of Door No.54-11-66, Gazetted Officers Colony, H.B.Colony, Visakhapatnam 530022.
2. Smt.Kakarlapudi Sarojini Devi, aged around 59 years, Hindu, W/o. Suryanarayana Raju, resident of Door No.54-11-66, Gazetted Officers Colony, H.B.Colony, Visakhapatnam 530022.
3.Vytla Narayana Rao, aged around 48 years, Hindu, S/o. Janaki Ramayya, resident of Door No.50-96-8/2, Seethammadhara (North Extension), Visakhapatnam 530013.
…..Defendants
Suit for (a) mandatory injunction by directing the defendants to execute and register the open spaces etc., of approved layout No.1 of 2008 by way of Registered Gift Settlement Deed in favour of Kapuluppada Grampanchayat, Bheemunipatnam Mandal, Visakhapatnam represented by its Panchayat Secretary and for (b) a mandatory injunction by directing the defendants to execute necessary papers and documents so as to obtain release of plots Nos.16 to 34, 84 to 91 of approved layout 1/2008 mortgaged in favour of Visakhapatnam Development Authority, at the cost and expenses of the plaintiff and (c) to specifically enforce the Agreements dt.2-02-2007 and 27-05-2007 by directing the defendants to execute and register, at the cost and expenses of the plaintiff (or) alternatively, if the court comes to the conclusion that Specific Performance cannot be granted in such an event to award compensation of Rs. 2,72,47,320/- (Rupees Two Crores Seventy Two Lakhs Forty Seven Thousand Three Hundred and twenty only) under Section 21 of the Specific Relief Act, 1963 and for such other reliefs and for costs of the suit.
The value of the suit for the purpose of Court fee and jurisdiction is Rs.2,72,47,320/- (Rupees Two Crores Seventy Two Lakhs Forty Seven Thousand Three Hundred and Twenty only) and a Court fee of Rs. 2,74,926/- (Rupees Two Lakhs Seventy Four thousand Nine Hundred Twenty Six only) is paid under Sec.39(e) of APCF and S.V.Act.
…..Defendants
This suit has come up for arguments before me on 14-03-2022 in the presence of Sri.K.Ravi, Advocate for Plaintiff Sri.V.V.Ravi Prasad & J.V.Rama Krishna, Advocates for D1 & D2 57 Spl.Judge, C.C/VSP COS 2/2018 (Old OS.No.389/2012) and Sri.N.S.V.Reddy, Advocate for 3rd defendant and this matter having heard and stood over for consideration till this day, this Court doth judgment: and
DECREE
1.that the suit be and the same is hereby dismissed; and
2.that there shall be no order as to costs.
Given under my hand and seal of the Court, this the 13 th day of June, 2022.
Sd/-XXX
Special Judge for trial and Disposal of
Commercial Disputes, Visakhapatnam
MEMORANDUM OF COSTS.
No cost memo is filed on either sides.
Sd/-XXX
Spl.Judge Commercial Court/VSP * The copy of schedule is herewith attached.